Pavement Preservation & MSTU Road Paving Programs
Pavement Preservation
Current and Upcoming Projects
Projects that are in progress and scheduled next are shown in the tentative paving schedule below. Important: The schedule is subject to change based on weather, contractor availability and other factors.
Tentative Paving Schedule
April 15-19, 2024 | Work Hours | Following 2 weeks | Work Hours |
Citrus Hill Rd | Day | Beacon Groves Blvd | Day |
East Grovehill Rd | Day | Beacon Point Blvd | Day |
East Groveleaf Ave | Day | Blossom Cir | Day |
East Orangecrest Ave | Day | Blue Ridge Ave | Day |
East Orangeside Road | Day | Citrus Hill Ln | Day |
Groveland Rd | Day | Citrus Valley Cir | Day |
Hill Rd | Day | East Orangehill Ave | Day |
N Green Ridge Pl | Day | Green Hollow Dr E | Day |
S Ridge Pl | Day | Grove Lake Cir | Day |
West Groveleaf Ave | Day | Grove Ridge Rd | Day |
West Orangecrest Ave | Day | Grove Valley Ave | Day |
Grovecrest Ave | Day | ||
Grovepark Rd | Day | ||
Grovepark Rd | Day | ||
Groveview Ln | Day | ||
Knoll Ave N | Day | ||
Knoll Ave S | Day | ||
Knoll St E | Day | ||
Knoll St W | Day | ||
N Citrus Way | Day | ||
Orangepointe Ave | Day | ||
Orangeside Rd | Day | ||
Peak St | Day | ||
Summit St | Day |
Overview
Pavement preservation is completed to protect the base material of our roads and minimize pavement issues, such as potholes or rutting. Most importantly, pavement preservation allows the County to stretch taxpayer dollars further by providing a greater return on investment.
For every $1 spent on pavement preservation, we save an estimated $6 to $10 or more in future reconstruction costs. By resurfacing at the right time, we can extend the life of the pavement at a much lower cost than reconstructing the roadway at a later date.
Pavement preservation projects are also socially responsible and ecologically sustainable, utilizing fewer non-renewable resources than reconstruction projects and causing fewer traffic delays with shorter duration projects.
Roadways are selected based on condition inspection, location groupings and the right timing to apply treatment before the roadway needs more expensive reconstruction measures.
The funding source for pavement preservation is the Penny for Pinellas.
Municipal Services Taxing Unit Roadway Program
The Municipal Services Taxing Unit (MSTU) Roadway Program addresses roadways that don’t currently meet County design standards. These roadways are being improved under the MSTU Roadway Program. Staff assess categories and prioritize each of the County’s MSTU roadways.
- Category I: Roadways that require little to no engineering or prep work and can easily be paved.
- Category II: Roadways that require roadway widening to reach the standard minimum width, some engineering, possible permitting and prep work.
- Category III: Roadways that require extensive design work, permitting, utility work and possible right-of-way acquisition.
Roadways are selected for paving based on condition inspection, location groupings and the right timing to apply treatment before the roadway needs more expensive reconstruction measures.
The funding source for Municipal Services Taxing Unit Roadway Program is the General Fund.